Expediting Generator Interconnection Procedures Act of 2025
- Introduced
- Committee
- House
- Senate
- President
- Law
- Introduced
- April 24, 2025
- Sponsor
- · D–FL
- Recorded roll calls
- None recorded
Forwarded by Subcommittee to Full Committee (Amended) by Voice Vote.
Read FactVote summary
The bill would require the Federal Energy Regulatory Commission to initiate, within 180 days of enactment, a rulemaking to accelerate and improve procedures for interconnecting electric generation and energy storage projects. The Commission would be required to issue a final rule within 18 months, including requirements concerning modeling, risk tolerance, cost-effective reliability solutions, information sharing, queue management, and timely network upgrades; the bill would not alter transmission-system cost allocation under existing Federal Power Act ratemaking authority.